Packaging for machinery starts with preparing the machine, not choosing a box. Drain fluids, lock moving parts and shield control panels and machined faces. Bolt the machine to a skid that carries its weight, enclose it in triple wall board or a timber crate to suit the lift and journey, seal out moisture and mark the centre of gravity.
Prepare the machine before it is packed
Most transit damage to machinery is done before any packaging goes on. A reservoir left full weeps past a seal, a carriage left free runs the length of its slideway every time the vehicle brakes, and a hanging control pendant takes the first knock from a forklift. Machine packaging for shipping starts with the machine itself.
Fluids
Oils, coolant and fuel find their way past seals once a machine tilts. The principle is to drain what the manufacturer's instructions say should be drained, cap or plug open ports, and record what was left in. Some fluids carry their own transport rules, so check with the carrier or forwarder before booking. Clean and dry a machine that has run on coolant before wrapping it, because film sealed over wet metal holds the moisture in.
Moving parts
Tables, heads, carriages and slides are run to the transit position the manufacturer specifies and locked, often with transit brackets supplied for the purpose. Doors and guards are tied shut, and loose items such as handwheels, chucks and tooling are removed, labelled and boxed separately so nothing travels around inside the crate. Where an axis could still turn, block it against a strong point on the casting, never a cover panel.
Control panels and machined faces
Control panels, screens and pendants are the parts most easily broken and slowest to replace. Detach and box them separately where the design allows; where they stay fitted, cover them with a rigid shield of board or foam-faced board that stands clear of the screen. Slideways and ground tables need a fitted foam pad specified by density against knocks, and bare metal is usually wrapped or interleaved with VCI paper or film, which releases a corrosion inhibitor into the enclosed air and works best sealed inside the barrier film described below.
The skid: base design and bolting down
A skid is the base the machine is bolted to: timber bearers or runners, decked where the load needs spreading, sized to the footprint and built for forklift entry. Every lift, brake and set-down passes through it.
Designing the base
Start from the machine's own feet, pads or bolt holes, and put the bearers directly beneath them rather than spanning between them. Levelling feet are usually backed off or removed so the weight rests on the machine base, not a threaded stud. Space the runners for fork entry from the sides the machine will be handled from. A lathe with a heavy headstock or a press with its motor at the top needs the base designed around where the weight is, not around the geometric centre.
Bolting down
Strapping alone rarely holds machinery: a strap slips along a smooth casting or slackens as the load settles, and a tall machine on straps will rock. Bolt through the mounting holes into the bearers, with load-spreading plates or large washers so the bolts cannot pull through the timber. Strapping is then a secondary restraint, specified by breaking strain and kept off finished surfaces with edge protection, as our guide to polypropylene, PET and steel strapping explains.
Triple wall case or timber crate
With the machine on its skid, the enclosure is a separate decision: a triple wall corrugated case, often a sleeve and lid lowered over the skid, or a timber crate built around it. A hybrid is common in mid-weight equipment packaging: a timber skid takes the weight and bolts, a triple wall hood takes the stacking.
| Machine and journey | Triple wall case on a skid | Timber crate |
|---|---|---|
| Bench or small machine, UK pallet route | Usually the right answer | Rarely needed |
| Floor-standing, forklift handled only | Works where little is stacked above | Where weight or stack load is beyond the board |
| Lifted by crane or sling | Not suitable | Needed, with base and frame designed for the lift |
| Tall or top-heavy | Possible with internal bracing | Better: the frame braces against tipping |
| Long sea journey or storage | Possible in a container, with barrier and desiccant | Preferred for long, humid, heavily handled trips |
| Stored outside or on open deck | Unsuitable | Suited, with a sheeted or boarded roof |
| International shipment | Board outside ISPM 15; a timber skid is not | Solid timber treated and marked |
Triple wall is often lighter and cheaper than a timber case for machines that do not genuinely need timber. Where the crate has to be built and the machine packed into it, that labour sits with our export packing and crating service; skid materials, case, barrier and corrosion protection are specified together under industrial packaging for heavy and engineering goods.
ISPM 15 on international shipments
Solid wood packaging material shipped internationally, including skids, bearers, battens and crates, falls under ISPM 15: it must be treated and carry the IPPC mark, and that includes moves between Great Britain and the EU. Panels made wholly of processed wood, such as plywood or OSB, are outside the standard, but the solid bearers they are fixed to are not, and corrugated board is not covered at all. The wider export picture is in our guide to packaging products for international delivery.
Lifting points and centre of gravity
Machinery is rarely balanced. A headstock, motor or hydraulic power pack can put the centre of gravity well off centre and high above the base, and whoever lifts the crate cannot see any of it. The outside of the crate should show:
- the centre of gravity, on at least two adjacent sides so it can be read in both directions;
- sling points where the crate is designed for a crane lift, and only there;
- fork entry positions, and any side that must not be forked;
- gross weight, orientation arrows and, where needed, do not stack.
A crane lift is only safe when the base and frame are designed for it: slinging a triple wall case, or a crate never built for a sling, crushes the top and loads the walls in a direction they cannot take. Tilt and shock indicators on the outside tell the receiving site whether the machine was tipped or dropped before anyone opens it.
For machinery the order is prepare, bolt down, enclose, seal, mark. A good case on an unprepared machine still arrives damaged.
Keeping moisture out
Moisture damage appears weeks later as rust on slideways and corroded contacts. The usual build is a sealed barrier enclosure: a barrier film base sheet goes on the skid before the machine is set down, then a cover or bag of barrier film is drawn over the machine and sealed to it. Desiccant sachets inside absorb the moisture trapped at sealing and what passes through the film on the way. The quantity depends on the enclosed volume, the film, the journey length and the conditions, so it is calculated rather than guessed.
Pad sharp corners so they cannot puncture the film, and seal where bolts pass through the base sheet, because one open hole lets humid air in for the whole trip. A humidity indicator card lets the receiver check conditions before opening. Temperature swings matter too: a container that warms by day and cools at night forms condensation under an unsealed cover, and the water collects on the coldest surface, usually bare metal.
Documentation that travels with the machine
The machine arrives at a site where nobody saw it packed, so the paperwork is part of the pack:
- a packing list in a pouch outside the crate, with a copy inside;
- a record of what was drained, what was left in, and which loose items were boxed separately;
- transit locks marked in a bright colour, with a note to remove them before the machine is powered;
- gross weight, net weight and crated dimensions;
- photographs of the machine on its skid and inside its barrier before the case was closed.
Crated weight and dimensions also decide whether the machine can go through a pallet network or needs a vehicle with a tail lift or crane, and pallet transport and distribution is booked against those figures. For export, customs and shipping documents are arranged through your forwarder.
Get machinery packaging specified
Send us the machine's weight, dimensions and a few photographs, how it will be lifted and where it is going. We specify the skid, the case, the moisture protection and the marking together, and quote against that specification.
Frequently asked questions
What is the best packaging for machinery?
It depends on the weight, the lifting method and the journey. Most machines are bolted to a timber skid, sealed in barrier film with desiccant, then enclosed in a triple wall case or a timber crate. Crane-lifted, very heavy or outdoor-stored machines usually need timber.
Do I need to drain oil before shipping a machine?
Drain what the manufacturer's instructions say to drain, cap the open ports and record what was left in. Some fluids carry their own transport rules, so check with your carrier or forwarder before booking.
Does a machinery crate need ISPM 15 treatment?
For international shipment, yes, if it contains solid wood: skids, bearers and battens must be treated and marked, including between Great Britain and the EU. Plywood or OSB panels and corrugated board are outside the standard.
Where should the centre of gravity be marked on a crate?
On at least two adjacent sides, so its position can be read in both directions, alongside the gross weight, the sling points and the fork entry positions.
How much desiccant does a machine need?
There is no single amount. It is calculated from the enclosed volume, the barrier film, the journey length and the conditions, and it only works inside a sealed enclosure.